Choose the carrier, line and year
Start with a carrier ID fromGET /insurance/carriers. A five-digit NAIC company
code is also accepted; the response returns the canonical managed carrier ID.
Schedule P uses lettered lines, such as R for products liability and D for
workers’ compensation. They are a separate scheme from the numbered statement
lines in state and line results. line is required. SUMMARY is the reported
all-lines page; do not add it to the lettered lines.
Set EFFECTIVE_API_KEY to your user API key, then request Part 2 (incurred) for
products liability in a specific statement year:
lossDevelopmentRows array and
nextCursor. Omit part to read parts 2 to 6. Omit statementYear to select the
carrier’s latest loaded Schedule P year. Each row is one printed row of one page:
id: pass unchanged to the item endpoint under the same carrier.naicCompanyCode: the source company, separate from the managed carrier ID.line,part,sectionandvariant: the Schedule P page. For lines F, H and R, section 1 is occurrence and section 2 is claims-made.sourceRow,rowTypeandaccidentYear: row 01 is prior years, rows 02 to 11 are accident years and row 12 is totals.development: the triangle cells by evaluation year, with their measure and unit.supplemental: other columns on the same row, such as one-year development.sources: the Schedule P page and statement year.
lossDevelopmentRows[].id into the item URL. For the 2024 accident year on
the occurrence page, the request is:
Interpret the values
Schedule P reports money in thousands. The API returns whole US dollars, so a
reported
52271 becomes 52271000. Claim counts are not scaled. Negative values
are preserved. The source load does not keep blank or zero cells, so a missing
evaluation year means blank or zero; it is not evidence of either.
The API returns what the schedule reports. It does not calculate development
factors, ultimates, loss ratios or sums. Part 1, Part 7 loss-sensitive contracts
and a mapping to numbered statement lines are not available.
Read the interrogatories
The interrogatories answer questions about the schedule, such as whether reserves are discounted (question 4) and whether claim counts are per claim or per claimant (question 6):year for the latest loaded year. Each source company has its own section.
topic is a short label, not the filed question text. Monetary answers are whole
US dollars; questions 5.1 and 5.2 are reported in thousands and scaled. Blank text
is null. The 2018 and 2019 loads store blank numbers as 0, so a zero in those
years does not prove a reported zero.
Continue and recover
Lists default to 50 rows;limit accepts 1–200. Follow nextCursor with the same
filters and limit. An omitted statement year stays pinned during traversal. Cursors
expire after 24 hours; restart without the cursor after invalid_cursor. Imported
values can change between calls; this is not a frozen snapshot.
dataset_not_enabled(403): request NAIC access from support.statutory_data_not_found(404): no loaded Schedule P data for that carrier and year. This does not prove the carrier failed to file.- Empty
lossDevelopmentRows: the year is loaded, but the line or part has no rows. - Item
not_found(404): the row was removed, is unavailable, or belongs to another carrier. Return to the collection to discover current rows.